What we ask before sizing a battery energy storage system
Energy storage is an engineering decision made from site data. These are the inputs that determine whether storage is the right answer and, if so, what shape it takes.

Storage requirements are derived, not assumed. Before a system is configured we work from measured load behaviour, the tariff structure and a defined operating objective — peak reduction, backup duration, renewable firming, generator support or a combination.
From those inputs the requirement is translated into an energy and power basis, an enclosure format and an interconnection point. The battery system, power conversion and the site electrical infrastructure are then engineered as one interface, including protection coordination, metering and the physical and thermal installation arrangement.
Control strategy is defined with the site: what the system is dispatched for, how it interacts with existing generation and load, and how it is monitored and reported.
We also say so when storage is not the right answer for a site. A system that is sized against assumptions rather than measurements is expensive to correct after commissioning.
Further reading: Industrial Battery Energy Storage Systems — system configurations, applications and the assessment process for industrial sites.